Murray Rise Lead
Overview:
Construction of lead in watermain from Branxton town centre to new subdivision in Lower Belford.
Scope of work:
- Clearing and earthworks
- 3km of new watermain
- Completion of five underbores through roads, culverts and creek
- Reinstatement of pavements and driveways
Highlights and challenges:
- 280m long underbore to a depth of 19m through rock under Black Creek
- Construction of watermain undertaken alongside live traffic along New England Highway
- Working alongside high pressure gas, optic fibre and directly under overhead powerlines