Wollar Rail Track Reconditioning
Overview:
KCE were charged to recondition the Wollar section of rail track, including the stabilisation and shotcreting of cutting batters within a short-term track closure of 3 days.
Scope of work:
- 200m rail track reconditioning
- 300m shoulder ballast replacement
- Supply plant, equipment and supervision
- Site survey
Highlights and challenges:
The delivery of the track formation reconditioning was conducted in a highly constrained cutting due to the track being restricted at one end by a tunnel portal