Singleton Rail Track Reconditioning

Overview:

Track formation reconditioning was required on the Up Main North for 150m, near Singleton within the Australian Rail Track Corporation (ARTC) Hunter Valley Rail Corridor.

Scope of work:

  • 150m track formation reconditioning
  • Removal of the existing formation to the nominated design depth and width
  • Replacement with new formation, capping, ballast
  • Local drainage improvements
  • 300m shoulder ballast replacement on adjacent section of track

Highlights and challenges:

As with most rail projects, timing was critical for a successfully completed project. Despite the tight turnaround required, all earthworks were completed within the required 36-hour timeframe.