Wyndham Ridge
Overview:
Construction of 248 lots at Wyndham Ridge Estate
Scope of work:
- 66,000 cu.m of cut to fill
- 41,000t of pavement construction
- 4.4km of kerb & gutter
- 3.6km of stormwater drainage
- 3.2km of sewer main
- 4.0km of watermain
- 3.0km of service trenching (electrical, nbn and gas)
Highlights and challenges:
The construction works have encountered a significant amount of rock in both earthworks and trenching. This has required works to be flexible with multiple work areas to ensure productivity is maintained while removing the rock.